The difference between admeasurement and construction management contracts
The main differences between an admeasurement contract and construction management, are that the former is primarily for civil engineering projects. In both approaches a level of price uncertainty exists, in the latter though this price uncertainty can be clarified once the design is finalised and all contracts established, whereas the former is more open to the risk of cost quantities of work carried out differing from the quantities originally anticipated.
Admeasurement contracts are commonly used on civil engineering projects. Rates are provided in the contractor’s tender, either as part of the priced bill of quantities, or within a schedule of rates. Then the actual quantities of work carried out are measured and the rates are applied to those quantities. As a result, the quantities paid for may vary from the original estimate. The term ‘admeasurement’ is thought to have originated in the ICE Conditions of Contract measurement clauses, where it referred to establishing the difference between the final quantity of work carried out and the quantity originally anticipated.
Construction management is a procurement route in which the works are constructed by a number of different trade contractors, these trade contractors are contracted to the client but managed by a construction manager. The construction manager acts as an agent for the client, administering and co-ordinating the works contracts. A construction manager is generally appointed early in the design process so that their experience can be used to improve the buildability and packaging of proposals as they develop. Appointing a construction manager enables some trade packages to be tendered earlier than others, and sometimes, even before the design is completed. This can shorten the time taken to complete the project, however, it means that there will be price uncertainty until the design is complete and all contracts have been let.
[edit] Related articles on Designing Buildings
- Admeasurement.
- Bill of quantities.
- Consequential loss.
- Construction management.
- Contract conditions.
- Contract sum.
- Defined provisional sum.
- Difference between preliminaries and preambles.
- Extension of time.
- Preliminaries.
- Prime cost sum.
- Procurement route.
- Provisional sum.
- The difference between a prime cost sum and a provisional sum.
- Undefined provisional sum.
- Variations.
Featured articles and news
Government responds to the final Grenfell Inquiry report
A with a brief summary with reactions to their response.
A brief description and background to this new February law.
Everything you need to know about building conservation and the historic environment.
NFCC publishes Industry White Paper on Remediation
Calling for a coordinated approach and cross-departmental Construction Skills Strategy to manage workforce development.
'who blames whom and for what, and there are three reasons for doing that: legal , cultural and moral"
How the Home Energy Model will be different from SAP
Comparing different building energy models.
Mapping approaches for standardisation.
UK Construction contract spending up at the start of 2025
New construction orders increase by 69 percent on December.
Preparing for the future: how specifiers can lead the way
As the construction industry prepares for the updated home and building efficiency standards.
Embodied Carbon in the Built Environment
A practical guide for built environment professionals.
Updating the minimum energy efficiency standards
Background and key points to the current consultation.
Heritage building skills and live-site training.
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.