The difference between admeasurement and construction management contracts
The main differences between an admeasurement contract and construction management, are that the former is primarily for civil engineering projects. In both approaches a level of price uncertainty exists, in the latter though this price uncertainty can be clarified once the design is finalised and all contracts established, whereas the former is more open to the risk of cost quantities of work carried out differing from the quantities originally anticipated.
Admeasurement contracts are commonly used on civil engineering projects. Rates are provided in the contractor’s tender, either as part of the priced bill of quantities, or within a schedule of rates. Then the actual quantities of work carried out are measured and the rates are applied to those quantities. As a result, the quantities paid for may vary from the original estimate. The term ‘admeasurement’ is thought to have originated in the ICE Conditions of Contract measurement clauses, where it referred to establishing the difference between the final quantity of work carried out and the quantity originally anticipated.
Construction management is a procurement route in which the works are constructed by a number of different trade contractors, these trade contractors are contracted to the client but managed by a construction manager. The construction manager acts as an agent for the client, administering and co-ordinating the works contracts. A construction manager is generally appointed early in the design process so that their experience can be used to improve the buildability and packaging of proposals as they develop. Appointing a construction manager enables some trade packages to be tendered earlier than others, and sometimes, even before the design is completed. This can shorten the time taken to complete the project, however, it means that there will be price uncertainty until the design is complete and all contracts have been let.
[edit] Related articles on Designing Buildings
- Admeasurement.
- Bill of quantities.
- Consequential loss.
- Construction management.
- Contract conditions.
- Contract sum.
- Defined provisional sum.
- Difference between preliminaries and preambles.
- Extension of time.
- Preliminaries.
- Prime cost sum.
- Procurement route.
- Provisional sum.
- The difference between a prime cost sum and a provisional sum.
- Undefined provisional sum.
- Variations.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February